Post by CHC8485 on Jun 6, 2019 16:34:29 GMT -5
Nope. Parking.
|
|
|
Post by Pakachoag Phreek on Jun 15, 2019 9:27:15 GMT -5
From the webcam today (Saturday), they are working and it appears they are trying to finish most of the excavation for the bottom level before next week. This level is largely buried, with windows only on the north side. It is sort of a half basement, as the ground floor level above it has a significantly larger area.
And HC is storing the excavated dirt on campus, for a future use that is speculative, at best. The college stored dirt from the new parking lot as well, piling it by the east end of Luth.
|
|
|
Post by hc6774 on Jun 15, 2019 9:37:36 GMT -5
I believe the lowest level is campus police headquarters... any idea how much parking & where for cruisers et al?
|
|
|
Post by Pakachoag Phreek on Jun 15, 2019 11:03:12 GMT -5
From the renderings, there is a small lot, probably 6-8 spaces, at the west end, about where the one story entrance / foyer to the field house used to be. I think this lot will be mainly for the campus police. No other parking. There is a plaza at the east end, which can be used for deliveries. but not for parking. Not clear from the renderings where/how trash will be collected.
I think they are working today because they may be closing the Upper Campus Road come Monday. I had thought the reconstruction of this road would be mostly near Hogan, but I am now of the view they will re-construct between Hogan and College. There are beaucoups pre-cast concrete manholes sitting on the site/, I'm guessing in the old days, the stormwater runoff simply drained down towed College St. No longer. Proper street drains and manholes to a sewer pipe will be installed.
I am surprised at how little ledge there was/is. The college must have leveled the slope of the hill with dirt (mostly clay) fill back in the 1940s for the old field house.
|
|
|
Post by KY Crusader 75 on Jun 15, 2019 11:07:02 GMT -5
Construction projects are always interesting to me--love to see the way these buildings go up. Thanks, phreak for your expertise and insights on these projects.
|
|
|
Post by Pakachoag Phreek on Jun 17, 2019 7:01:00 GMT -5
This morning, they have closed off the Upper Campus Road between College St and Hogan. I assume this is for its reconstruction. ______________________________________________ I'm still lacking a floorplan, but as best as I can tell from four, quadrant renderings of the exterior, the two basketball courts are on the first floor running along the south side of the building, aligned east-west (the courts in the old field house were north south).
The elevated jogging track will be above the basketball courts, probably an oval 200' on its north and south segments, and 70-75 feet on the east and west segments, to obtain the 1/10th of a mile track. The track is cantilevered above the corner of the building on the southwest corner
The campus police offices are probably on the first floor, northwest corner.
Strength and conditioning equipment om the second floor, running the E-W length of the building and with a glass wall. The second floor is open (other than for the track) along the south side of the building. This allows half court heaves at the basket.
Other exercise rooms, e.g., yoga, cycle, etc. on the first floor below strength and conditioning.
On the ground floor, locker/equipment rooms for club sports. The ground floor, which runs along the north and NW sides of the building, does not extend to beneath the basketball courts, or to the NE corner of the building.
|
|
|
Post by purplehaze on Jun 18, 2019 10:41:23 GMT -5
PPhreek - I was looking at the webcam this morning and in the small area, extreme forefront of the picture (separate from the rec center dig), there is some excavation going on - what's that all about ?
|
|
|
Post by rgs318 on Jun 18, 2019 10:53:05 GMT -5
time capsule?
|
|
|
Post by Pakachoag Phreek on Jun 18, 2019 11:49:21 GMT -5
PPhreek - I was looking at the webcam this morning and in the small area, extreme forefront of the picture (separate from the rec center dig), there is some excavation going on - what's that all about ? I believe that is related to the reconstruction of the Upper Campus Road, and reconfiguring access to the loading docks at Hogan. They would want to finish the latter by mid-August. A few days ago, they slightly changed the field of view of the webcam, so one now sees only one tree stump in the 'island' where before there were two. There are still two stumps on the hill above Wheeler. goo.gl/maps/iUfpdHaiGEPJbDLh8^^^The two deciduous trees closest to the camera were cut down. goo.gl/maps/5SLACLVRRryCJaGq9^^^The two cut trees; the single shrub like tree in the island in the distance is long gone. goo.gl/maps/en9P6FZmFoGC2KFh6^^^The rather convoluted access to the Hogan loading dock(s). The deciduous tree nearest the camera has been cut. So I think they are planning to square off the road and 'ramp' to the loading dock at this point. Apparently all the beer consumed on campus is delivered here, and for beek trucks, this already was awkward to back in.
|
|
|
Post by hchoops on Jun 18, 2019 12:20:53 GMT -5
Easy solution Go dry
|
|
|
Post by Pakachoag Phreek on Jul 20, 2019 10:14:13 GMT -5
|
|
|
Post by hchoops on Jul 20, 2019 13:31:07 GMT -5
Fair comparison ? Doesn’t the Luth fill some students’ recreational needs and wants ?
|
|
|
Post by Pakachoag Phreek on Jul 20, 2019 16:33:54 GMT -5
Fair comparison ? Doesn’t the Luth fill some students’ recreational needs and wants ? Comparing Connell with (The Jo / Luth) By level at Connell First LevelPOOLS (in Lith) MULTI-ACTIVITY COURTS short field sports (no) LOCKER ROOMS (yes) OUTDOOR ADVENTURES CENTER (no) GOLF SIMULATOR (yes) CLIMBING AND BOULDERING WALLS (no) CLUB SPORT ATHLETIC TRAINING ROOM (unknown) Second Level-
FITNESS NEIGHBORHOODS (yes, but consolidated) MULTIPURPOSE ROOMS (yes) SPIN STUDIO (yes) POOL SPECTATOR BALCONY (NA) MIND-BODY STUDIO (?, yes if yoga) 'Third level GYM AND COURTS four hoops courts (two courts at The Jo) TENNIS three courts (no) FITNESS NEIGHBORHOODS (yes, but consolidated) MULTIPURPOSE ROOMS (yes) CLUB SPORT AND INTRAMURAL OFFICE SUITE (probably) Fourth level FITNESS NEIGHBORHOODS (yes, but consolidated) RACQUETBALL AND SQUASH COURTS two each (@ Luth???) JOGGING TRACK (yes) WELLNESS ROOM (??) FITNESS RAMP (no) www.bc.edu/content/dam/files/top/advancement/general/FY18/images/connell/Connell-Rec-Ctr-booklet-low-res.pdf
|
|
|
Post by Pakachoag Phreek on Aug 7, 2019 12:19:56 GMT -5
From the webam, the structural steel has begun arriving and the ironworkers will soon be busy.
They are laying a base course for future paving of the re-aligned Upper Campus Road. So as mentioned by another poster, a rough course of asphalt may indeed be in place by month's end.
IMO, use of the road will be restricted until construction is further along. The southeast corner of The Jo is flush against the re-aligned road, I expect at least one lane of the road will be needed for construction of this particular corner. From the renderings,the southwest corner is cantilevered, and also is close to the road.
The building is a polygon, not a rectangle, and the north-south axis appears to be significantly longer than what appears in the renderings.
|
|
|
Post by rgs318 on Aug 7, 2019 12:36:20 GMT -5
Thanks pak.
|
|
|
Post by HCFC45 on Aug 8, 2019 15:03:10 GMT -5
Ironworkers were busy today! Watched for quite a bit as the crane operator was lifting beams in place. Wish that webcam had a "zoom in" feature.!
|
|
|
Post by KY Crusader 75 on Aug 8, 2019 17:18:18 GMT -5
It takes some real experience/talent to operate those big cranes
|
|
|
Post by Crucis#1 on Aug 8, 2019 20:05:16 GMT -5
Ironworkers were busy today! Watched for quite a bit as the crane operator was lifting beams in place. Wish that webcam had a "zoom in" feature.! If you are using a tablet, ie. an iPad, you can zoom in on areas of the construction site.
|
|
|
Post by HCFC45 on Aug 8, 2019 21:45:22 GMT -5
Ironworkers were busy today! Watched for quite a bit as the crane operator was lifting beams in place. Wish that webcam had a "zoom in" feature.! If you are using a tablet, ie. an iPad, you can zoom in on areas of the construction site. Thanks for the heads up! I'll try it tomorrow! !
|
|
|
Post by Pakachoag Phreek on Aug 9, 2019 7:43:20 GMT -5
I was searching for info on whether DiMeo is also the general contractor for the Center for Creativity and the Arts -- they are, indicating that HC had followed advice to have the same contractor build both buildings and save some money -- and came across an info blog by a Worcester trades union rep.
The rep listed major upcoming construction jobs in Greater Worcester, and noted that HC's general policy was to have construction contracts valued at more than $1 million be done with union labor.
The ironworkers on the construction site are probably from the Boston local, which has 3500 members. Same as for the operating engineer on the crane.
From the webcam, they seem to be very efficient and methodical.
|
|
|
Post by Crucis#1 on Aug 9, 2019 12:20:38 GMT -5
The former guard shack outside of Hogan has a sign stating DiMeo Field Office.
It appears a lot of progress was made this week in site preparation of the Arts Center.
|
|
|
Post by CHC8485 on Aug 20, 2019 7:40:40 GMT -5
Quick look at the webcam this morning shows new pavement being rolled from in front of Hogan down to the new Rec Center. And from the looks of it, they appear ready to pave all the way out to College Street. Expect they want that gate open for the arrival of new Students a week from Saturday.
|
|
|
Post by hc6774 on Aug 20, 2019 8:23:16 GMT -5
It looks like the island that divided the accesses to the south/up hill entrance side and the west side of Hogan has been paved over.
|
|
|
Post by Pakachoag Phreek on Aug 21, 2019 8:51:27 GMT -5
I am quite sure the realigned Upper Campus Road took a good chunk out of the north 'lawn; of the Jesuit residence. goo.gl/maps/fKzYbR6MGNde3tDVAThe southeast corner of The Jo is so close to the Upper Campus Road that I expect they will need bollards to protect the building. I think this south part of the edifice is home to the two basketball courts, and it is only one floor.
|
|
|
Post by Crucis#1 on Aug 21, 2019 10:28:23 GMT -5
I thought the running track will be above the two basketball courts.
|
|